CE library paige solomon  2017-03-07 09:26
 
Hello,
In a new project, how would I go about assigning CE values taken from SRMAtlas data base to my transition list? I have tried to create an optimization library under "Trans Settings" but there is an issue w my product ion format, and I am not certain this is the appropriate procedure. I exported the transition list from SRMAtlas as a skyline file, but the CEs do not automatically transfer.

Thanks!
 
 
Brendan MacLean responded:  2017-06-09 10:03
Hi Paige,
At the moment, you would need to build your own optimization library by organizing the values with the correct identifier information and pasting into the optimization library form grid.

I have posted an issue to track progress on making this easier:

https://skyline.ms/issues/home/issues/details.view?issueId=521

Can't promise, though, when that would happen.

Thanks for your feedback.

--Brendan